Melton Recreation Reserve

A new pavillion will be built at Melton Recreation Reserve.  The pavilion redevelopment will service football, cricket and netball use at the reserve and will be located along the northern wing of the oval in a more centralised location with optimal viewing of the sportsground. The building will replace the existing pavilion and will include female friendly change rooms, umpires rooms, community social space, meeting room, kitchen, and kiosk.

A new pavilion will be constructed allowing for the community groups to transition from the old pavilion into the new prior to the old pavilion being demolished and the new carpark being completed. 

The project will be completed in two stages. Stage 1 being the pavilion which is expected to be completed by June-July 2024, stage 2 is the sealed car park which is currently expected to be completed by November-December 2024

The Victorian Government is contributing $3.3 million through the 2020-21Community Sports Infrastructure Loans Scheme.

May update

Construction of the double-storey timekeeper and coaches box started in April.

Demolition of the old pavilion and construction of a new car park is also expected to finish before the end of the year, allowing community groups time to transition from the old pavilion before its demolition.

Workers have completed the roof, ceiling grids and plastering and are in the process of finishing cladding, painting, hardware fit offs, tiling and flooring.

March update

The new pavilion at Melton Recreation Reserve is on track for completion in July.

The pavilion structure, door frames and windows are now complete, with cladding, plastering, joinery and tiling well underway.

Construction of double-storey timekeeper and coaches boxes will kick off in April, with a new car park to be completed at the reserve by the end of the year.

January update

Works are continuing and the slab is complete with the framing almost complete. The next lot of work to commence will be the roof, stormwater  and brickwork.

The project is on track to have the pavilion completed by July 2024.

 

December update

The following works have been completed so far:

  • Retaining Wall
  • All in ground services
  • Footings
  • Slab 90% complete
  • Steel (has been fabricated)

Works that are about to commence:

  • Frame
  • Roof
  • Brickwork 
    melton-rec-reserve-december.png

     

October update

Construction commenced at Melton Recreation Reserve on 5 September.

The following works have been completed so far:

  • Site Establishment
  • Demolishion and removal of the existing players shelters, storage sheds and portable toilets.  
  • Bulk earth works
  • Set out/surveying  works

Works that are currently underway

  • Retaining wall – approx. 80% complete
  • In ground services have begun approx. 10%

August update

Procurement activities have concluded with H.Troon being appointed as the Principal Contractor to undertake the delivery of the works.Works are expected to begin by September 2023 and be completed by late 2024.

 

    Location

    Reserve Road, Melton 3337  View Map