Westwood Drive Road and Bridge Construction

  • Project value$8.7m
  • Completion Date14 December 2018
westwood-july.jpg

 The construction of Westwood drive began in January 2018 and opened in December 2018.

The completion of Westwood Drive Road and Bridge between Tenterfield Drive and Fydler Avenue, is a critical road link in the Eastern Corridor, and will take significant pressure off Caroline Springs Boulevard and Gourlay Road.

Key features of this project will include:

  • 950m of new road (Tenterfield Drive to the bridge, then the bridge to Fydler Ave)
  • Bridge over the Kororoit Creek
  • 3m wide Shared User Path running on the eastern side of the road
  • Connection of existing footpaths on the western side of the road
  • Noise walls next to existing houses on the new section of road.

Work completed so far:

April 2016 - January 2018 - Approval process with VicRoads and the Department of Environment, Land, Planning and Water.

April 2017 – Westwood Drive noise wall design consultation

August 2017 - Archaeologists carried out salvaging works and investigations required under the approved Cultural Heritage Management Plan.

August 2017 - Councillors approved the preferred construction contractor and passed a motion that allowed officers to award the contract upon approval from the Minister for Planning.

November 2017 - Council received the approvals from the Minister for Planning that allowed the award of the construction contract.  

January 2018 – Zoologists carried out pre-construction spotlighting checks for the Growling Grass Frog and Striped Legless Lizards

January 2018 – Construction contractors begin work.

February 2018 – Noise wall footings began along with boxing of road and footpaths.

April 2018 – Work on the bridge began. Noise wall footings complete.

May 2018 – Southern abutment concrete poured. Noise wall posts began to be installed.

June 2018 – Northern abutment concrete poured. Asphalting and kerb completed on the northern section of road

July 2018 – Southern abutment poured and bridge beams installed

August 2018 – Kerb complete for the entire length of the project. Footpath and shared path concreting begins. Bus stops for PTV installed.

September 2018 – Bridge parapets installed and rock beaching under the bridge starts

October 2018 – Bridge painting begins and noise walls are complete.

December 2018 - Road opened.

 

This video does not contain any dialog only music.

Location

Westwood drive, Burnside 3023  View Map

Google Map